3MW – Chennai, TamilnaduOwner’s Engineer

ACE Renewtech had the privilege of providing Project Management Consulting (PMC) with our sister concern of KCP Solar Industry as an EPC Player for BAP’s Solar Power Project located at Madhuranthakam of Kancheepuram District, Tamil Nadu, India.

  • Project Size : 3 MW
  • Project Type : Captive Consumption
  • Location : Chennai, Tamil Nadu
  • End Client : British Agro India Limited
  • EPC Contractor : KCP Solar Industry
  • Area Covered : 8 acres
  • Project Completion : 2019 Mar
  • First of its kind in Tamil Nadu designed with 1500V (DC) & 800V (AC)
  • Employed 90 kW String Inverters to reduce losses & to increase Efficiency
  • Successfully Commissioned in 70 Days Land Abridgement
  • Achieved Peak Efficiency up to 2.5 MW with 3 MW(DC)